PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Samarth ParadiseMahaRERA P52100077186

by Samarth Associates

25/1/23, Gajanan Colony, 411033

Aug 2026
Possession
38.2%
Built
0
Complaints
14
Units
High risk
  • Behind schedule. Possession is due Aug 2026 but construction is only at 38.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2026 per the RERA filing.

Official RERA facts

Registration
P52100077186
Status
New
Stage
Certificate Signed
Possession
August 2026originally February 2026
Construction
38.2% complete
Units sold
5 of 14

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2024
Floors
7
Unit mix
14 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Samarth Paradise โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Samarth Paradise. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.