PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SATYAM KASHISH PHASE IIMahaRERA P52100077554

by VIJAYALAXMI ASSOCIATES

SURVEY NO. 7, HISSA NO. 36, AMBEDKAR NAGAR KONDHWA BK, 411048

Mar 2029
Possession
62.3%
Built
0
Complaints
56
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100077554
Status
New
Stage
Certificate Signed
Possession
March 2029
Construction
62.3% complete
Units sold
5 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)45%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting50%
Community Buildingsnot started
Water conservation /Rain water harvesting35%
Energy managemcntnot started
Fire protection and fire safety requirements15%
Electrical meter room, sub-station, receiving station15%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2024
Floors
6
Unit mix
56 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SATYAM KASHISH PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SATYAM KASHISH PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.