Under construction

TULSI REYANSHMahaRERA P52100077557

by Tulsi Bidcon

284/1B, 284/2, 284/3, Lohgoan, 411047

Dec 2027
Possession
75.5%
Built
0
Complaints
62
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100077557
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
75.5% complete
Units sold
10 of 62

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2024
Floors
12
Unit mix
48 res ยท 14 comm
Architect
Studio 24

Buyer community

Connect with other buyers and owners of TULSI REYANSH โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TULSI REYANSH. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.