Aaiji Crystal Phase IIMahaRERA P52100077661
36/2/3/1, 36/2/2, 36/2/2/9, 67/1B/25/7,36/67/PLOT/A, pune, 411015
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P52100077661
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2026originally April 2026
- Construction
- 63% complete
- Units sold
- 34 of 120
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Mangesh Vitthalrao Dhadge
Possession extension history
- EA01042620515Revised to October 2026
The project commenced post to the outbreak of the COVID-19 pandemic. However, from March 2020 to February 2022, construction activities were severely affected due to nationwide lockdowns, movement restrictions, and mandatory safety protocols. The pandemic caused widespread disruption in the availability of skilled and unskilled labour, as well as in the supply chain for construction materials and equipment. These constraints resulted in prolonged inactivity and slow progress on site. Despite these unprecedented conditions, continuous efforts were made to sustain limited operations and mitigate the impact in compliance with government directives. 2. Labour Shortage and Migration Issues Following the pandemic, a substantial portion of the construction workforce migrated back to their native regions. This mass migration created a critical shortage of skilled manpower, significantly affecting productivity levels. Although the developer made persistent efforts to remobilize labour through contractors, the industry-wide shortage resulted in limited availability, delayed work sequencing, and slower progress across several work fronts. 3. Escalation in Material Costs and Financial Constraints Global economic volatility and geopolitical factors led to a sharp rise in the prices of essential construction materials such as cement, steel, sand, and fuel. This escalation in input costs placed an unexpected financial burden on the project and disrupted the planned cost structure. The resulting budgetary constraints required periodic rescheduling of procurement and execution activities, which consequently slowed down the pace of construction. 4. Inflationary Pressures and Increase in Construction Rates In addition to material cost escalation, inflation and an overall rise in construction rates further affected project economics. The continuous increase in labour wages, transportation charges, and subcontracting rates has made it difficult to maintain the original cost and time estimates. These macroeconomic conditions have further compounded delays in achieving targeted milestones.In anticipation of your understanding and cooperation, I would like to express my gratitude. We are committed to completing the project within the extended timeframe and ensuring compliance with all regulatory requirements.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2024
- Floors
- 18
- Unit mix
- 120 res ยท 0 comm
- Architect
- SOMNATH KERUR
- Plot / CTS / survey no.
- 36/2/3/1, 36/2/2, 36/2/2/9, 67/1B/25/7,36/67/PLOT/A
- Planning authority
- Pune Municipal Corporation
- Approved layout land
- 3,477.89 sq.m
- Land for this registration
- 3,477.89 sq.m
- Recreational open space
- 348 sq.m
- Permissible built-up area
- 14,000 sq.m
- Registered office
- SUNANDA APARTMENT
- North
- S No 36-2-3-1 Part
- South
- S No 36-2-2 MV Khese
- East
- S No 36-2-2 Part
- West
- S No 67 12Mtr Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 65252IFSC ICIC0003373ICICI Bank Ltd., Sunanda Apartment, Vishrantwadi, Pune, Maharashtra.411015
Commencement Certificate documents
- C C.pdf
- Aaiji Crystal Revised CC No 1156-25 Dt 30-06-25.pdf
Buyer community
Connect with other buyers and owners of Aaiji Crystal Phase II โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Aaiji Crystal Phase II. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.