DWARKA PROJECT 5MahaRERA P52100077980

by NAIKNAVARE HOUSING DEVELOPMENTS PVT LTD

88P,90 TO 94,95P,96,97P,113/2,122,123,124P,125,126/1,127,127/1,128/2,128/3,126/2, CHAKAN, 410501

Jun 2027
Possession
30.7%
Built
0
Complaints
143
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 30.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100077980
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
30.7% complete
Units sold
81 of 143

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Nov 2024
Floors
13
Unit mix
143 res ยท 0 comm
Architect
Gauri Hemant Naiknavare

Buyer community

Connect with other buyers and owners of DWARKA PROJECT 5 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DWARKA PROJECT 5. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.