DWARKA PROJECT 5MahaRERA P52100077980
by NAIKNAVARE HOUSING DEVELOPMENTS PVT LTD
88P,90 TO 94,95P,96,97P,113/2,122,123,124P,125,126/1,127,127/1,128/2,128/3,126/2, CHAKAN, 410501
- Behind schedule. Possession is due Jun 2027 but construction is only at 30.7%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100077980
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 30.7% complete
- Units sold
- 81 of 143
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Nov 2024
- Floors
- 13
- Unit mix
- 143 res ยท 0 comm
- Architect
- Gauri Hemant Naiknavare
Buyer community
Connect with other buyers and owners of DWARKA PROJECT 5 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching DWARKA PROJECT 5. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.