EWS BUILDING - WING B
by Joyville Shapoorji Housing Private Limited
6/7/9/10/6 (part), Shewalwadi, 412307
- Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100078550
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2027
- Construction
- 30.9% complete
- Units sold
- 12 of 129
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Litigation record2 cases
- Civil Judge Senior Devision PuneCase Regular Civil Suit No 185 of 2022/2022Summons stage
- Sub Divisional Officer Haveli PuneCase Tenancy Appeal No 959 of 2018/2018Admission Stage
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2024
- Floors
- 13
- Unit mix
- 129 res ยท 0 comm
- Architect
- AMITVAA SPACCES
- Plot / CTS / survey no.
- 6/7/9/10/6 (part)
- Planning authority
- Pune Metropolitan Region Development Authority
- Approved layout land
- 1,011.63 sq.m
- Land for this registration
- 1,011.63 sq.m
- Recreational open space
- 308.75 sq.m
- Permissible built-up area
- 7,978.43 sq.m
- Registered office
- SP Centre
- North
- EWS Building - Wing A
- South
- Tower 6
- East
- Village Road
- West
- EWS Building - Wing D
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62301IFSC ICIC0000323ICICI Bank Ltd., Bombay Hub, Z Wing, Kamla Mill Compound, Senapati Bapat Marg, Lower Parel, Mumbai.400013, Maharashtra
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of EWS BUILDING - WING B โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching EWS BUILDING - WING B. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.