Under construction

INFINITY PLANET A WING

MahaRERA P52100078903High risk

by TULIP PROPERTIES

Gat No. 105,106,107,108,113,114,115, Moshi Pune, 412105

Official record
Jun 2027
Possession
0%
Built
0
Complaints
389
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Mortgaged to a lender (โ‚น18 Cr). MahaRERA's financial encumbrance declaration shows this project has โ‚น18 Cr secured against a lender โ€” a lender's claim can outrank a buyer's if the promoter defaults.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 0%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100078903
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
0% complete
Units sold
19 of 389

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Litigation record2 cases

  • CIVIL COURT SR DIVISION PUNECase 380/2021
    PENDING
  • CIVIL JUDGE JR DIVISION PIMPRICase 131/2021
    PENDING
Mortgaged to a lender

MahaRERA's financial encumbrance declaration shows this project has โ‚น18 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's โ€” worth raising with the builder before booking.

Landowner

Mrs. Shital Shivaji Khedekar alias shital Tanaji A, Mr Prakash Ratanchand Metha, Mr. Laxman Vithoba Alhat, Mrs. Shila Bhousaheb alias Sonba Kedari, Mr. Lalit Sohanlal Jain, M/s Kubera Landmarks LLP, Mrs. Laxmibai Mahadu Alhat, Mrs. Harshada Shambhu Borate alias Harshada Arvind, Mrs. Amruta Harish Alhat, Mr. Harish Arvind Alhat, Mrs. Sujata Arvind Alhat, Mrs. Arvind Mahadu Alhat, Mrs. Monali Sagar Alhat, Mr. Sagar Tanaji Alhat, Mrs. Sushma Tanaji Alhat, Mr. Tanaji Mahadu Alhat, Mrs. Hemlata Ajay Girame, Mrs. Sarika Hemant Alhat, Mr. Hemant Pandurang Alhat, Mr. Swati Sachin Alhat, Mr. Sachin Pandurang Alhat, Mrs. Nanda Pandurang Alhat, Mr. Pandurang Mahadu Alhat, Mrs. Dipali Ajay Bhiwasankar, Mr. Nitin Bapurao Karne, Mr. Uday Bapurao Karne, Mr. Bapurao Gangaram Karne, Mrs. Sujata Dhananjay Alhat, Mr. Dhananjay Murlidhar Alhat, Mrs. Kalpana Vijay Alhat, Mr. Vijay Murlidhar Alhat, Ms. Shradha Raju Alhat, Mrs. Sunita Raju Alhat, Mr. Raju Murlidhar Alhat, Mrs. Yamunabai Murlidhar Alhat, Mr. Murlidhar Sadhu Alhat, Mrs. Pratibha Sanjay Alhat, Mr. Sanjay Anant Alhat, Mrs. Sadhna Ravikant Mate, Mrs. Sharmila Jalindar Jadhav, Mr. Ajay Shantaram Alhat, Mr. Prashant Pandurang Raut, Mr. Rahul Pandurang Raut, Mrs. Manda alias Mandakini Dilip Gaikwad, Mr. Sitaram Ramchandra Tamhane, Mr. Yogesh Dnyaneshwar Alhat, Mrs. Vaishali Kailas Alhat, Mr. kailas Dnyaneshwar Alhat, Mr. Abhijit Santosh Alhat, Mrs. Lata Santosh Alhat, Mr. Aniket Vilas Alhat, Mrs. Sangita Vilas Alhat, Mr. Vilas Baban Alhat, Mr. Ashish Kailash Alhat, Mrs. Ashwini Kailash Alhat alias Ashwini Rajkiran, Mrs. Janabai Kailash Alhat, Mr. Kailash Baban Alhat, Mrs. Kajal Akshay Alhat, Mr. Akshay Shantaram Alhat, Mrs. Komal Ajay Alhat, Mrs. Vandana Shantaram Alhat, Mr. Shantaram Baban Alhat, Mrs. Savita Chandrakant Satav, Mrs. Rupali Yogesh Alhat, Mr. Santosh Dnyaneshwar Alhat, Mrs. Sushila Dnyaneshwar Alhat, Mr. Dnyaneshwar Vithoba Alhat, Mrs. Pramila Uttam Lendghar, Mrs. Sangita Chandrakant Jadhav, Mrs. Suman Anant Alhat, Mr. Antu alias Anant Sadhu Alhat, Mrs. Rohini Nivrutti Alhat, Mrs. Priyanka Nivrutti Alhat, Mrs. Shital Nivrutti Alhat alias Shital Yogesh Ban, Mr. Rutiraj Nivrutti Alhat, Mr. Rushilesh Nivrutti Alhat, Mr. Abhishek Vilas Alhat, Mr. Kartik Kisanrao Landge

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2025
Floors
9
Unit mix
0 res ยท 389 comm
Architect
Landmark Design Group
Plot / CTS / survey no.
Gat No. 105,106,107,108,113,114,115
Planning authority
Pimpri Chinchwad Municipal Corporation
Approved layout land
1,650 sq.m
Land for this registration
1,650 sq.m
Recreational open space
1,560 sq.m
Permissible built-up area
15,560.34 sq.m
Registered office
LA CASITA
Plot boundaries
North
E WING
South
30m WIDE DEHU ALANDI ROAD
East
GAT NO 98
West
GAT NO 111 AND B WING
Parking
182 four-wheeler14 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • AXIS BANK โ€” 162701
    IFSC UTIB0003144
    GR FL SHOP NO04 05 AND 06 BIZ SNO 2031 RAVET PIMPRI CHINCHWAD PUNE MAHARASHTRA 412101

Commencement Certificate documents

  • Commencement.pdf
  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of INFINITY PLANET A WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INFINITY PLANET A WING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.