PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Aqura Prime

MahaRERA P52100078984Caution

by Aqura Builder and Developer Private Limited

S. No. 29A/1/3/8/2/2/1, C.T.S. No. 7737 and 7740, Plot No 6 + 7, Village - Wadgaonsheri, Taluka - Haveli, District - Pune 411014, Ramwadi Wadgaon Sheri, 411014

Official record
Jul 2028
Possession
27.3%
Built
0
Complaints
23
Units
Caution
  • Possession delayed ~1 yr. Originally promised Apr 2027, now proposed Jul 2028 per the RERA filing.

Official RERA facts

Registration
P52100078984
Status
New
Stage
Certificate Signed
Possession
July 2028originally April 2027
Construction
27.3% complete
Units sold
0 of 23

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Shri Sadguru Hambirbaba Sahakari Gruharachna Sanst

Possession extension history

  • EA23062621485Revised to July 2028

    The project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with required quality standards and to safeguard the interests of allottees. Hence, we request MahaRERA to kindly grant an extension of the project completion date.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2025
Floors
8
Unit mix
23 res ยท 0 comm
Architect
Jay Aeram and Associates Architects and Planners
Plot / CTS / survey no.
S. No. 29A/1/3/8/2/2/1, C.T.S. No. 7737 and 7740, Plot No 6 + 7, Village - Vadgaon-Sheri, Taluka - Haveli, District - Pune 411014
Planning authority
Pune Municipal Corporation
Approved layout land
1,165.2 sq.m
Land for this registration
1,165.2 sq.m
Recreational open space
0 sq.m
Permissible built-up area
4,660.8 sq.m
Registered office
-
Plot boundaries
North
CTS Number 7737 and 7739 PMC School
South
9 Meters DP Road and Decent Residency
East
CTS Number 7740 and 7739 parts and PMC School
West
Society Internal Road and Decent Residency
Parking
7 four-wheeler12 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • AU SMALL FINANCE BANK LIMITED โ€” 3050
    IFSC AUBL0002544
    USMALLFINANCEBANKLTD,SHOPNO.1AND2,GULMOHARPARTMENTS,USHACO-OPSOCIETY,EASTSTREET,PUNE-411001,MAHARASHTRA

Commencement Certificate documents

  • CC-3049-23 DT 28-02-2024_compressed.pdf

Buyer community

Connect with other buyers and owners of Aqura Prime โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aqura Prime. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.