Golan Heights
by DIVYAYASHA BUILDERS PROMOTERS AND DEVELOPERS
CTS No- 17/1, 17/2 B & 18B, Lonavala, 410401
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100079189
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally November 2026
- Construction
- 57.3% complete
- Units sold
- 0 of 14
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Joy Maria Santos Golan
Possession extension history
- EA15052620974Revised to June 2027
We, Divyayasha Builders, Promoters and Developers, the promoter of the project Golan Heights (Registration No. P52100079189) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project. The delay has primarily been caused due to pending internal work. Further, we are currently facing a shortage of tiles due to the ongoing war situation, as the tiles manufacturing factory has been closed for the past two months. This has directly impacted the progress of internal finishing work. Due to the above circumstances, the internal work remains incomplete, and we are consequently unable to proceed with the sale of units. Given the situation, we kindly request an extension until 30-06-2027 to complete the project and fulfil all regulatory requirements.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2025
- Floors
- 3
- Unit mix
- 4 res ยท 10 comm
- Architect
- Vastu Designers
- Plot / CTS / survey no.
- CTS No- 17/1, 17/2 B & 18B
- Planning authority
- Lonavla Municipal Corporation
- Approved layout land
- 1,214.06 sq.m
- Land for this registration
- 1,214.06 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 2,599.59 sq.m
- Registered office
- F Ward
- North
- D P Road
- South
- Railway Land
- East
- D P Road
- West
- Part of R S No- 223
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF MAHARASHTRA โ 90119IFSC MAHB0000075194, G.WARD, DR SISODIA BLDG, TILAK ROAD, LONAVALA 410401
Commencement Certificate documents
- Commencement certificate.pdf
Buyer community
Connect with other buyers and owners of Golan Heights โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Golan Heights. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.