Under construction

Hillview Residency Building E

MahaRERA P52100079466High risk

by KUMAR BEHARAY PROPERTIES LLP

S No 69/5B/2, 69/8/1 and 70/1 to 17A/1 PLOT NO 2, Kothrud, 411038

Official record
Jun 2027
Possession
62.9%
Built
0
Complaints
76
Units
High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100079466
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
62.9% complete
Units sold
19 of 76

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Litigation record3 cases

  • CIVIL COURTCase 309/20/2017
    PENDING
    Status: Ongoing
  • HIGH COURTCase 27/2017 AND 29/2017/2017
    PENDING
    Status: Ongoing
  • CIVIL JUDGE SENIOR DIVISION PUNECase 650/70/2014
    PENDING
    Status: Ongoing

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Mar 2025
Floors
21
Unit mix
76 res ยท 0 comm
Architect
VISHAL JAGDISH DESHPANDE
Plot / CTS / survey no.
S No 69/5B/2, 69/8/1 and 70/1 to 17A/1 PLOT NO 2
Planning authority
PUNE MUNICIPAL CORPORATION
Approved layout land
4,138.46 sq.m
Land for this registration
4,138.46 sq.m
Recreational open space
7,702.38 sq.m
Permissible built-up area
10,359.87 sq.m
Registered office
CONSTRUCTION HOUSE
Plot boundaries
North
S No 69
South
By 18 Meter Service Road and Green Belt
East
By S No 66 67 and 68 adjacent by partly Plot No 1
West
By 12 Meter Service Road and National Highway No 4
Parking
111 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 67265
    IFSC ICIC0006240
    ICICI Bank Ltd., FP 195, CTS 853, Signature Bhamburda, Shivaji Nager, Bhandarkar Road,Pune.411004

Commencement Certificate documents

  • 9 COMMENCEMENT CERTIFICATE 19th flr.pdf

Buyer community

Connect with other buyers and owners of Hillview Residency Building E โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Hillview Residency Building E. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.