SHREE SADGURU RESIDENCY
43A/11/12/13A/2/3, 43A/9A/11A,43A/11/12/13A/2/1, KIWALE, 412101
- Behind schedule. Possession is due Feb 2027 but construction is only at 40.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100079638
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2027
- Construction
- 40.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
NIVRUTTI YESHWANT JADHAV, DINESH NIVRUTTI JADHAV
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2025
- Floors
- 9
- Plot / CTS / survey no.
- 43A/11/12/13A/2/3, 43A/9A/11A,43A/11/12/13A/2/1
- Planning authority
- PIMPRI CHINWAD PUNE
- Approved layout land
- 694.47 sq.m
- Land for this registration
- 694.47 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 2,208 sq.m
- Registered office
- SHREE SADAGURU RESIDENCY
- North
- SR NO 43A 9 11A 2 2 1B 1 20 LAND
- South
- SR NO 43A 9A 11A LAND
- East
- SR NO 43A BALANCE LAND
- West
- ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- TJSB SAHAKARI BANK LTD โ 144462IFSC TJSB0000032THOMAS BAZAR, KIWALE, DEHUROAD, PUNE-412101
Commencement Certificate documents
- CC_11zon.pdf
Buyer community
Connect with other buyers and owners of SHREE SADGURU RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE SADGURU RESIDENCY. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.