PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Ganga Capitol One

MahaRERA P52100080094High risk

by SHREE BALAJI ASSOCIATES PUNE LLP

Survey No. 62 CTS No. 1696 Plot No. 13 & 14, Pune, 411036

Official record
Dec 2029
Possession
3.6%
Built
0
Complaints
42
Units
High risk
  • Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
  • Mortgaged to a lender (โ‚น80 Cr). MahaRERA's financial encumbrance declaration shows this project has โ‚น80 Cr secured against a lender โ€” a lender's claim can outrank a buyer's if the promoter defaults.

Official RERA facts

Registration
P52100080094
Status
New
Stage
Certificate Signed
Possession
December 2029
Construction
3.6% complete
Units sold
0 of 42

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Litigation record4 cases

  • NOCase NO/0000
    NOT APPLICABLE
    Status: Closed
  • NOCase 00/0000
    NOT APPLICABLE
    Status: Closed
  • NOCase 00/0000
    NOT APPLICABLE
    Status: Closed
  • NOCase 00/0000
    NOT APPLICBALE
    Status: Closed
Mortgaged to a lender

MahaRERA's financial encumbrance declaration shows this project has โ‚น80 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's โ€” worth raising with the builder before booking.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2025
Floors
16
Unit mix
0 res ยท 42 comm
Architect
Creative Designs Mr Sanjay Kumar Giri
Plot / CTS / survey no.
Survey No. 62 CTS No. 1696 Plot No. 13 & 14
Planning authority
PUNE MUNCIPAL CORPORATION
Approved layout land
4,000 sq.m
Land for this registration
4,000 sq.m
Recreational open space
0 sq.m
Permissible built-up area
24,560.6 sq.m
Registered office
SAN MAHU COMMERCIAL COMPLEX
Plot boundaries
North
Adj S No 62 P
South
30 M Wide DP Road
East
Adj S No 62 P
West
Adj S No 62 P
Parking
189 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • INDUSIND BANK โ€” 75761
    IFSC INDB0000002
    2401,GEN.THIMMAYYA RD. (CANTONMENT), PUNE - 411 001.

Commencement Certificate documents

  • Ganga Capitol One CC.pdf
  • Ganga Capitol One CC Verification Email.pdf

Buyer community

Connect with other buyers and owners of Ganga Capitol One โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ganga Capitol One. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.