Maavi Shree Ashirwad
CTS No. 675 P, Kothrud-South, 411038
- Possession delayed ~3 yrs. Originally promised Dec 2027, now proposed Dec 2030 per the RERA filing.
Official RERA facts
- Registration
- P52100080158
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2030originally December 2027
- Construction
- 38.4% complete
- Units sold
- 3 of 60
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Shree Ashirwad Co- Operative Housing Society Ltd
Possession extension history
- EA20042620664Revised to December 2030
We, Maavi Spaces Unit 1, the promoter of the project Maavi Shree Ashirwad (Registration No. P52100080158) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We respectfully request an extension due to a typographical error that occurred during the project registration process. At the time of registering the project on the MahaRERA portal, the project completion date was mistakenly mentioned as 31-12-2027 due to an inadvertent administrative and typographical oversight during submission. We would like to clarify that the project comprises 2 wings ( Wing A + Wing B) with Ground + 6 upper floors each and considering the scale and nature of the development, it is practically not feasible to complete the project within such a short period of approximately 1.5 years. From the very beginning, our planned and targeted completion timeline for the project has been 31-12-2030, and we were aware that the project could not realistically be completed by 31-12-2027. The incorrect completion date was purely a typographical error at the time of project registration. We have taken immediate corrective measures to rectify the same and ensure that all records reflect the intended timeline accurately. We further submit that if the correction is not carried out at this stage and the extension is sought only closer to the erroneously mentioned completion date, it may create confusion and misunderstanding amongst the allottees regarding the actual completion timeline of the project. Further, non-completion within the mistakenly mentioned date may unnecessarily cause dissatisfaction and frustration amongst the allottees despite the actual project planning being aligned with the revised timeline. In view of the above circumstances, we humbly request your kind consideration and seek an extension of time until 31-12-2030 to complete the project and fulfil all regulatory requirements.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2025
- Floors
- 7
- Unit mix
- 60 res ยท 0 comm
- Plot / CTS / survey no.
- CTS No. 675 P
- Planning authority
- Pune Municipal Corporation
- Approved layout land
- 2,880 sq.m
- Land for this registration
- 2,880 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 8,843.92 sq.m
- Registered office
- Deccan Gymkhana
- North
- By Portion of Survey No 11 LIC Vinit Co-Operati
- South
- Survey No 9 Part
- East
- Open Space
- West
- Part of 9-3-3-A of Shri R V Bajaj
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 67265IFSC ICIC0006240ICICI Bank Ltd., FP 195, CTS 853, Signature Bhamburda, Shivaji Nager, Bhandarkar Road,Pune.411004
Commencement Certificate documents
- Commencement certificate 15-10-2024.pdf
Buyer community
Connect with other buyers and owners of Maavi Shree Ashirwad โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Maavi Shree Ashirwad. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.