PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Maavi Shree Ashirwad

MahaRERA P52100080158High risk

by Maavi Spaces Unit 1

CTS No. 675 P, Kothrud-South, 411038

Official record
Dec 2030
Possession
38.4%
Built
0
Complaints
60
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2027, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P52100080158
Status
New
Stage
Certificate Signed
Possession
December 2030originally December 2027
Construction
38.4% complete
Units sold
3 of 60

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Shree Ashirwad Co- Operative Housing Society Ltd

Possession extension history

  • EA20042620664Revised to December 2030

    We, Maavi Spaces Unit 1, the promoter of the project Maavi Shree Ashirwad (Registration No. P52100080158) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We respectfully request an extension due to a typographical error that occurred during the project registration process. At the time of registering the project on the MahaRERA portal, the project completion date was mistakenly mentioned as 31-12-2027 due to an inadvertent administrative and typographical oversight during submission. We would like to clarify that the project comprises 2 wings ( Wing A + Wing B) with Ground + 6 upper floors each and considering the scale and nature of the development, it is practically not feasible to complete the project within such a short period of approximately 1.5 years. From the very beginning, our planned and targeted completion timeline for the project has been 31-12-2030, and we were aware that the project could not realistically be completed by 31-12-2027. The incorrect completion date was purely a typographical error at the time of project registration. We have taken immediate corrective measures to rectify the same and ensure that all records reflect the intended timeline accurately. We further submit that if the correction is not carried out at this stage and the extension is sought only closer to the erroneously mentioned completion date, it may create confusion and misunderstanding amongst the allottees regarding the actual completion timeline of the project. Further, non-completion within the mistakenly mentioned date may unnecessarily cause dissatisfaction and frustration amongst the allottees despite the actual project planning being aligned with the revised timeline. In view of the above circumstances, we humbly request your kind consideration and seek an extension of time until 31-12-2030 to complete the project and fulfil all regulatory requirements.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2025
Floors
7
Unit mix
60 res ยท 0 comm
Plot / CTS / survey no.
CTS No. 675 P
Planning authority
Pune Municipal Corporation
Approved layout land
2,880 sq.m
Land for this registration
2,880 sq.m
Recreational open space
0 sq.m
Permissible built-up area
8,843.92 sq.m
Registered office
Deccan Gymkhana
Plot boundaries
North
By Portion of Survey No 11 LIC Vinit Co-Operati
South
Survey No 9 Part
East
Open Space
West
Part of 9-3-3-A of Shri R V Bajaj
Parking
59 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 67265
    IFSC ICIC0006240
    ICICI Bank Ltd., FP 195, CTS 853, Signature Bhamburda, Shivaji Nager, Bhandarkar Road,Pune.411004

Commencement Certificate documents

  • Commencement certificate 15-10-2024.pdf

Buyer community

Connect with other buyers and owners of Maavi Shree Ashirwad โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Maavi Shree Ashirwad. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.