Nexus Westia
41/48(P) & 41/47/2/2(P), Punawale, 411033
- Mortgaged to a lender (โน15 Cr). MahaRERA's financial encumbrance declaration shows this project has โน15 Cr secured against a lender โ a lender's claim can outrank a buyer's if the promoter defaults.
- Behind schedule. Possession is due Jun 2027 but construction is only at 15.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100080184
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 15.9% complete
- Units sold
- 11 of 83
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
MahaRERA's financial encumbrance declaration shows this project has โน15 Cr secured against a lender. If the promoter defaults, the lender's claim can outrank a buyer's โ worth raising with the builder before booking.
Landowner
Shankar Baburao Darshale, Prabhakar Shankar Darshale, Vikram Shankar Darshale, Navnath Sitaram Darshale, Balasaheb Bajirao Darshale, Suresh Ramchandra Darshale, Pooja Anil Salunke, Sarika Vishal Mali, Prafulla Kashinath Darshale, Rohidas Bajirao Darshale, Dipak Rajaram Darshale, Dattatray Rajaram Darshale, Chandrakant Nathu Darshale, Rahul Chandrakant Darshale, Mayur Chandrakant Darshale, Rohan Suresh Darshale, Roshan Suresh Darshale, Ramchandra Nathu Darshale, Nilesh Ramchandra Darshale, Ajay Ramchandra Darshale, Sachin Nivrutti Shinde, Kusum Bajirao Darshale, Ranjana Hiraman Jagtap, Sangita Rohidas Darshale, Prajakta Sachin Mate, Chaya Balasaheb Darshale, .Ankita Balasaheb Darshale, Omkar Balasaheb Darshale, Rajaram Baburao Darshale, Subhadra Rajaram Darshale, Manisha Deepak Darshale, Meghnath Deepak Darshale, Somanath Deepak Darshale, Surekha Dattatrya Darshale, Anuja Dattatrya Darshale, Nanda Khandu Alhat, Sunita Sanjay Raut, Sitabai Shankar Darshale, Vaishali Prabhakar Darshale, Pratik Prabhakar Darshale, Priyanka Prabhakar Darshale, Pallavi Vikram Darshale, Mangal Sunil Karne, Ratnamala Ramchandra Jamdade, Sitaram Baburao Darshale, Kantabai Sitaram Darshale, Prachi Navnath Darshale, Surekha Gulab Bankar, Akshay Surendra Pandhare, Surendra Ramchandra Pandhare, Jyoti Sanjay Kalamkar, Manisha Manoj Fulvare, Vidya Raju Bhujbal, Reshma Ajit Mehtre, Kisan Dashrath Darshale, Arjun Dashrath Darshale, Aarti Kashinath Darshale, Prajwala Kashinath Darshale
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2025
- Floors
- 14
- Unit mix
- 66 res ยท 17 comm
- Plot / CTS / survey no.
- Survey No. 41/47/2/2, 41/48, Village Punawale, Taluka Mulshi, District Pune
- Planning authority
- Pimpri Chinchwad Municipal Corporation
- Approved layout land
- 2,360 sq.m
- Land for this registration
- 2,360 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 7,012.14 sq.m
- Registered office
- Nexus Group
- North
- By Remaining Property Of Survey No 41-48
- South
- By 18 Mtr Road
- East
- By Property Of Survey No 43
- West
- By Remaining Property Of Survey No 41-48
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62299IFSC ICIC0000321ICICI Bank Ltd., Shop No. 7,8,9 & 10, Empire Square, City Survey No. 4746, Next to Auto Cluster, Off Pune Mumbai Highway, Chinchwad, Pune, Maharashtra - 411019
Commencement Certificate documents
- CC PCMC 27 12 2024 updated.pdf
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of Nexus Westia โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Nexus Westia. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.