AQUILA
207/208/1A/1B/3, Malwadi, 411028
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
Official RERA facts
- Registration
- P52100080347
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2028originally March 2028
- Construction
- 25.9% complete
- Units sold
- 14 of 53
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Litigation record1 case
- Civil Judge Senior Division PuneCase 325/2011Evidence Part HeardStatus: Ongoing
Landowner
Anuradha Dilip Tupe, Indrajeet Dilip Tupe, Samruddhi Dilip Tupe
Possession extension history
- EA30062501862Revised to September 2028
We, the Promoter of the registered project βAQUILAβ bearing MahaRERA Registration No. P52100080347, hereby submit this declaration for extension of the project completion date under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. At the time of project registration, the date of completion was declared as 31/03/2028. However, we now seek to revise and extend the project completion timeline by a period of six months, i.e., up to 30/09/2028. The reason for seeking this extension is that, although the project registration for AQUILA was granted recently on 26/05/2025, a considerable amount of time was consumed in addressing and resolving the various queries raised by MahaRERA during the scrutiny process, particularly concerning the increased plot area. This led to an unforeseen delay in the grant of registration, thereby impacting the overall execution timeline of the project. We have duly paid the requisite additional fees towards the increased plot area and have also filed a correction application bearing No. PCRCN05062512127 dated 24/06/2025 to reflect the same. This entire process contributed to the delay in commencement of actual project activities. At present, we are in a position to commence the project with full momentum. Accordingly, we are requesting this extension solely to realign the project timeline with the actual start of on-ground activities. It is also pertinent to mention that no units have been sold in the project as of date. We, therefore, request you to kindly consider our application for extension of the completion date and grant approval accordingly.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2025
- Floors
- 20
- Unit mix
- 53 res Β· 0 comm
- Architect
- Ar. Mangesh Gotal
- Plot / CTS / survey no.
- 207/208/1A/1B/3
- Planning authority
- Pune Municipal Corporation
- Approved layout land
- 3,595.74 sq.m
- Land for this registration
- 3,595.74 sq.m
- Recreational open space
- 126.18 sq.m
- Permissible built-up area
- 8,854.63 sq.m
- Promoter contact
- Dilip Baburao Tupe
- Registered office
- -
- North
- Adjoining 24 Meters Wide DP Road
- South
- Adjoining CTS No 4317 P
- East
- Adjoining Tower E
- West
- Adjacent Road
Project bank account
The RERA-designated account this project's payments should go to β verify before wiring any money.
- HDFC BANK β 53917IFSC HDFC0006003SHOP NO 11 TO 20 T SQUARE TUPE PATIL ROAD NEXT TO MARVEL RITZ HADAPSAR PUNE MAHARASHTRA 411028
- HDFC BANK β 53917IFSC HDFC0006003SHOP NO 11 TO 20 T SQUARE TUPE PATIL ROAD NEXT TO MARVEL RITZ HADAPSAR PUNE MAHARASHTRA 411028
- HDFC BANK β 53917IFSC HDFC0006003SHOP NO 11 TO 20 T SQUARE TUPE PATIL ROAD NEXT TO MARVEL RITZ HADAPSAR PUNE MAHARASHTRA 411028
- HDFC BANK β 53917IFSC HDFC0006003SHOP NO 11 TO 20 T SQUARE TUPE PATIL ROAD NEXT TO MARVEL RITZ HADAPSAR PUNE MAHARASHTRA 411028
Commencement Certificate documents
- doc08806720250324203316_rotated.pdf
- AQUILA TOWER F PLOT INCREASE FINAL.pdf
- Approved CC.pdf
Buyer community
Connect with other buyers and owners of AQUILA β compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet β start one and connect with the next buyer researching AQUILA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.