Under construction

Varad ViharMahaRERA P52200001508

by Shashikant Chandrakant Rahinj

Plot no A 19 and A 20 S No 24/2A/2, Ahmadnagar (M Corp.), 414003

Mar 2019
Possession
40%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 40%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2019 per the RERA filing.

Official RERA facts

Registration
P52200001508
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
40% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Jul 2017
Floors
7

Buyer community

Connect with other buyers and owners of Varad Vihar โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Varad Vihar. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.