All RERA projects
๐๏ธ
Under construction
ROYAL PALMS APARTMENTMahaRERA P52200001966
28/5 s.no.14/1a/2, rasnenagar, 414001
Nov 2020
Possession
33.6%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised May 2019, now proposed Nov 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 33.6%.
Official RERA facts
- Registration
- P52200001966
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2020originally May 2019
- Construction
- 33.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Landscaping & Tree Planting50%
Street Lightingdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 7
Buyer community
Connect with other buyers and owners of ROYAL PALMS APARTMENT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ROYAL PALMS APARTMENT. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.