Under construction

Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi AhmednagaMahaRERA P52200019849

by NASHIK HOUSING & AREA DEVELOPMENT BOARD

109 110, Savedi, 414003

Dec 2023
Possession
50.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 50.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52200019849
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
50.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
6

Buyer community

Connect with other buyers and owners of Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi Ahmednaga โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi Ahmednaga. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.