๐Ÿ—๏ธ
Under construction

MAULI TOWERMahaRERA P52200050742

by MAYUR ANAND SHINDE

Survey No.141/1B, Plot No.5+6/1, Kedgaon, Ahmednagar, KEDGAON, 414005

Dec 2025
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.

Official RERA facts

Registration
P52200050742
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
LIFT WITH BACKUPdone

Building & registration

RERA registered
Apr 2023
Floors
6
Plot / CTS / survey no.
Survey No.141/1B, Plot No.5+6/1, Kedgaon, Ahmednagar
Planning authority
Others
Approved layout land
370 sq.m
Land for this registration
370 sq.m
Recreational open space
0 sq.m
Permissible built-up area
946.91 sq.m
Promoter contact
MAYUR ANAND SHINDE
Registered office
DYAN
Plot boundaries
North
9 M WIDE ROAD
South
SURVEY NO 141 2P
East
PLOT NO 7
West
PLOT NO 6 2
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 68269
    IFSC ICIC0007588
    SUPA

Commencement Certificate documents

  • Mauli Tower CC.pdf

Buyer community

Connect with other buyers and owners of MAULI TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAULI TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.