SHOBHA HERITAGE
Survey No 320/2,Plot No 3, SAVEDI, 414003
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 45.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.
Official RERA facts
- Registration
- P52200050972
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026
- Construction
- 45.5% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
TEJNIL DEVELOPERS, Swanand Mukund Rasal, Sudhanshu Mukund Rasal, Mukund Bhagwan Rasal
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2023
- Floors
- 6
- Plot / CTS / survey no.
- Survey No 320/2,Plot No 3
- Planning authority
- Others
- Approved layout land
- 270.13 sq.m
- Land for this registration
- 270.13 sq.m
- Permissible built-up area
- 756.85 sq.m
- Promoter contact
- Nilesh Vasantrao Chavan
- Registered office
- 602 NITYANAND PARK
- North
- Open Space
- South
- 12 M Wide Road
- East
- Plot No 4
- West
- Plot No 2
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 49285IFSC HDFC0000900SR 56/1 KAWADENAGAR NEW SANGAVI PUNE 411027
Commencement Certificate documents
- Rasal-Commencement certificate.pdf
Buyer community
Connect with other buyers and owners of SHOBHA HERITAGE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHOBHA HERITAGE. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.