Under construction

Park StreetMahaRERA P52400020794

by N B DONGARE PROPERTIES

Survey No. 34/A/1, 34/B/2, Opp. Mount Litera Zee School, 413512

Mar 2022
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52400020794
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2019
Floors
5

Buyer community

Connect with other buyers and owners of Park Street โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Park Street. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.