PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI DIGAMBAR APARTMENTMahaRERA P52400022801

by NIWARA GRUHNIRMAN PVT LTD

4,5, MORE NAGAR, 413512

Mar 2022
Possession
9.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 9.8%.

Official RERA facts

Registration
P52400022801
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
9.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Oct 2019
Floors
6

Buyer community

Connect with other buyers and owners of SAI DIGAMBAR APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI DIGAMBAR APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.