Under construction

TULSIBAAGMahaRERA P52400053613

by SUSHMA SHAILESH KULKARNI

22/1, PLOTNO 11 TO 56 & 85 TO 92, TULSIBAAG, 413531

Dec 2027
Possession
38.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Nov 2024, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52400053613
Status
New
Stage
Certificate Signed
Possession
December 2027originally November 2024
Construction
38.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Plantingdone
Street Lightingnot started
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Nov 2023
Floors
1

Buyer community

Connect with other buyers and owners of TULSIBAAG โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TULSIBAAG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.