- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52400078754
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 107.3% complete
- Units sold
- 8 of 70
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jan 2025
- Floors
- 5
- Unit mix
- 70 res ยท 0 comm
- Architect
- Chintan Seth
- Plot / CTS / survey no.
- SURVEY No. 159/2 , Final Plot No 4
- Planning authority
- Latur Municipal Corporation
- Approved layout land
- 2,340.8 sq.m
- Land for this registration
- 2,340.8 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 6,977.44 sq.m
- Registered office
- Vishwaraj Empire
- North
- Land belongs to Aradhya
- South
- 12 Meter wide Road
- East
- Plot No 3
- West
- Plot No 5
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 63663IFSC ICIC0001699ICICI Bank Ltd., Radhekrishna Cts 3424, M.H.No.R6/942, Kamdar Road, Latur, Latur Dist., Maharashtra.413512
Commencement Certificate documents
- CC.pdf
Buyer community
Connect with other buyers and owners of Rushabh Platinum โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Rushabh Platinum. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.