Shree ResidencyMahaRERA P52600005699

by HEMENT DAMU PINGALE

147/8426/A1, Solapur (M Corp.), 413001

Oct 2020
Possession
86.8%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 86.8%.

Official RERA facts

Registration
P52600005699
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
86.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of Shree Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shree Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.