PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

INDRADHANU-Phase-2MahaRERA P52600006002

by M/S Ganesh Ramchandra Apte

WING-Z-2,164/1/A, Laxmi Peth, 413001

Mar 2029
Possession
72.3%
Built
0
Complaints
29
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jul 2023, now proposed Mar 2029 per the RERA filing.

Official RERA facts

Registration
P52600006002
Status
New
Stage
Certificate Signed
Possession
March 2029originally July 2023
Construction
72.3% complete
Units sold
3 of 29

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths98%
Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)98%
Storm Water Drains98%
Landscaping & Tree Planting98%
Street Lighting98%
Community Buildings98%
Treatment And Disposal Of Sewage And Sullage Water98%
Water conservation /Rain water harvesting98%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station98%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
0 res ยท 29 comm
Architect
Zeeshan E Mundewadi

Buyer community

Connect with other buyers and owners of INDRADHANU-Phase-2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INDRADHANU-Phase-2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.