All RERA projects
๐๏ธ
Under construction
MANJUL PLAZAMahaRERA P52600013753
CSNO 1316 A 1316 B, INDIRANAGAR, 413307
Dec 2026
Possession
79.5%
Built
0
Complaints
18
Units
High risk
- Possession delayed ~4 yrs. Originally promised May 2023, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52600013753
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally May 2023
- Construction
- 79.5% complete
- Units sold
- 10 of 18
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Building & registration
- RERA registered
- Oct 2017
- Floors
- 5
- Unit mix
- 16 res ยท 2 comm
Buyer community
Connect with other buyers and owners of MANJUL PLAZA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MANJUL PLAZA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.