Under construction

INDRADHANU-Phase-IVMahaRERA P52600014920

by M/S Ganesh Ramchandra Apte

CST NO.8436, 8437, F.P. NO. 164/1/A, Laxmi Peth, 413001

Dec 2028
Possession
46.9%
Built
0
Complaints
126
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jan 2026, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52600014920
Status
New
Stage
Certificate Signed
Possession
December 2028originally January 2026
Construction
46.9% complete
Units sold
82 of 126

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains80%
Landscaping & Tree Planting80%
Street Lighting80%
Community Buildings90%
Treatment And Disposal Of Sewage And Sullage Water30%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station40%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2018
Floors
21
Unit mix
126 res ยท 0 comm
Architect
Zeeshan E Mundewadi

Buyer community

Connect with other buyers and owners of INDRADHANU-Phase-IV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INDRADHANU-Phase-IV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.