Under construction

Ray Nagar Housing Project Phase 2MahaRERA P52600017956

by Vasant Vihar Realty Pvt Ltd

978,979,981,982,1053,1055,1056,1057,1038,1041,58,59,1039,1087,1104,728,729,74,75,76,77,70,722, KUMBHARI TO DARGANHALLI ROAD, 413007

Dec 2027
Possession
67.6%
Built
0
Complaints
7,882
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52600017956
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
67.6% complete
Units sold
419 of 7882

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2018
Floors
6
Unit mix
7881 res ยท 0 comm
Architect
Pravin Deodhar
Public authority
Ray Nagar Housing Co operative Societies Federation Ltd South Solapur

Buyer community

Connect with other buyers and owners of Ray Nagar Housing Project Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ray Nagar Housing Project Phase 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.