Ray Nagar Housing Project Phase 2MahaRERA P52600017956
by Vasant Vihar Realty Pvt Ltd
978,979,981,982,1053,1055,1056,1057,1038,1041,58,59,1039,1087,1104,728,729,74,75,76,77,70,722, KUMBHARI TO DARGANHALLI ROAD, 413007
- Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52600017956
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2025
- Construction
- 67.6% complete
- Units sold
- 419 of 7882
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Sept 2018
- Floors
- 6
- Unit mix
- 7881 res ยท 0 comm
- Architect
- Pravin Deodhar
- Public authority
- Ray Nagar Housing Co operative Societies Federation Ltd South Solapur
Buyer community
Connect with other buyers and owners of Ray Nagar Housing Project Phase 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Ray Nagar Housing Project Phase 2. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.