PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Pearl ResidencyMahaRERA P52600026964

by Fairdeal constructions

Plot 90 S No. 10/2, Hotgi Road, 413003

Feb 2024
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Feb 2024) has passed with construction at 0%.

Official RERA facts

Registration
P52600026964
Status
New
Stage
Certificate Signed
Possession
February 2024
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Electrical meter room, sub-station, receiving station10%
Open Parkingdone

Building & registration

RERA registered
Nov 2020
Floors
6
Plot / CTS / survey no.
Plot 90 S No. 10/2
Planning authority
Others
Approved layout land
249.01 sq.m
Land for this registration
249.01 sq.m
Permissible built-up area
445.35 sq.m
Registered office
Motiwala constructions
Plot boundaries
North
Plot 89
South
Road
East
Open Space
West
Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF INDIA โ€” 15118
    IFSC BKID0000710
    Solapur

Commencement Certificate documents

  • PEARL RESIDENCY 1 (2)-merged_compressed.pdf

Buyer community

Connect with other buyers and owners of Pearl Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Pearl Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.