Dec 2026
Possession
72.7%
Built
0
Complaints
66
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Jan 2025, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52600030559
Status
New
Stage
Certificate Signed
Possession
December 2026originally January 2025
Construction
72.7% complete
Units sold
48 of 66

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA31052501376Revised to December 2026

    The project was delayed due to prolonged approval timelines from statutory authorities, which impacted our construction schedule. Shortages in labor and critical materials disrupted site work, causing unforeseen delays in project execution.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)done

Building & registration

RERA registered
Sept 2021
Floors
9
Unit mix
54 res ยท 12 comm
Plot / CTS / survey no.
Plot S.NO 32/A3/A2
Planning authority
Solapur Municipal Corporation
Approved layout land
1,014.74 sq.m
Land for this registration
1,014.74 sq.m
Permissible built-up area
3,043.36 sq.m
Registered office
Monalisa Complex
Plot boundaries
North
Road
South
Road
East
Plot
West
Plot

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • IDBI BANK โ€” 61294
    IFSC IBKL0478MCB
    Jule Solapur

Commencement Certificate documents

  • Adobe Scan 29 Aug 2021_compressed.pdf

Buyer community

Connect with other buyers and owners of Balaji Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Balaji Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.