Under construction

PMAY BARSHI NAGAR PARISHAD AHPMahaRERA P52600047436

by BARSHI NAGAR PARISHAD

GAT NO.1196/1 AND 1196/2, BARSHI NAGAR PARISHAD, 413401

Sept 2026
Possession
37.3%
Built
0
Complaints
1,607
Units
High risk
  • Behind schedule. Possession is due Sept 2026 but construction is only at 37.3%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52600047436
Status
New
Stage
Certificate Signed
Possession
September 2026originally December 2025
Construction
37.3% complete
Units sold
166 of 1607

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA29042620778Revised to September 2026

    We respectfully submit that the construction of the above-mentioned project is presently under progress. However, the project could not be completed within the stipulated timeline i.e., December 2025, due to the following unavoidable circumstances beyond our control: 1. Drought Conditions (2023โ€“24): The project was adversely affected due to severe drought conditions prevailing during the year 2023โ€“24, resulting in a slowdown of construction activities for approximately four months. 2. Technical Issues on PMAY Portal: Due to issues relating to gender correction on the PMAY portal, we were unable to upload beneficiary details in a timely manner. This resulted in a delay of approximately four months in receipt of the Government subsidy. 3. Heavy Rainfall (2025โ€“26): Excessive rainfall during the year 2025โ€“26 further impacted the progress of construction work. 4. Financial Constraints of EWS Beneficiaries: The beneficiaries under the project, belonging to the Economically Weaker Section (EWS), faced difficulties in availing housing loans from banks due to the absence of income tax returns. Consequently, there was a delay in receipt of payments towards the flats. We further submit that, as per the above-referred letter issued by the Ministry of Housing and Urban Affairs, Government of India, the PMAY-U Mission has been extended up to 30th September 2026 for completion of already sanctioned and ongoing projects. The present project squarely falls within the said category. We are pleased to inform that a scheduled bank has now agreed to extend housing loan facilities to the beneficiaries, and the process has recently commenced, which is expected to improve the pace of collections and construction. In view of the above facts and circumstances, and considering the extension granted by the Government of India under PMAY-U, we humbly request your good office to grant an extension of time up to 30th September 2026 for completion of the project. A copy of the above-referred Government letter dated 27.02.2026 is enclosed herewith for your kind perusal. We request your kind consideration and approval.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths23%
Water Supply23%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drains25%
Landscaping & Tree Planting20%
Street Lighting23%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting25%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station23%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2022
Floors
5
Unit mix
1602 res ยท 5 comm
Plot / CTS / survey no.
GAT NO.1196/1 AND 1196/2
Planning authority
MAHADA
Approved layout land
57,354 sq.m
Land for this registration
57,354 sq.m
Recreational open space
5,735.72 sq.m
Permissible built-up area
1,87,568.08 sq.m
Registered office
BARSHI NAGAR PARISHAD
Plot boundaries
North
PART OF GAT NO 1196
South
GAT NO 1097
East
PIMPALGAON DHAS 30MTR ROAD
West
ROAD AND GAT NO 1062
Parking
2025 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF MAHARASHTRA โ€” 90095
    IFSC MAHB0000051
    RAICHURKAR BUILDING GULAL ROAD BARSHI

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE.PDF
  • FORMAT D.pdf
  • MAHADA PERMISSION.PDF

Buyer community

Connect with other buyers and owners of PMAY BARSHI NAGAR PARISHAD AHP โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PMAY BARSHI NAGAR PARISHAD AHP. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.