PMAY BARSHI NAGAR PARISHAD AHPMahaRERA P52600047436
GAT NO.1196/1 AND 1196/2, BARSHI NAGAR PARISHAD, 413401
- Behind schedule. Possession is due Sept 2026 but construction is only at 37.3%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2026 per the RERA filing.
Official RERA facts
- Registration
- P52600047436
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally December 2025
- Construction
- 37.3% complete
- Units sold
- 166 of 1607
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA29042620778Revised to September 2026
We respectfully submit that the construction of the above-mentioned project is presently under progress. However, the project could not be completed within the stipulated timeline i.e., December 2025, due to the following unavoidable circumstances beyond our control: 1. Drought Conditions (2023โ24): The project was adversely affected due to severe drought conditions prevailing during the year 2023โ24, resulting in a slowdown of construction activities for approximately four months. 2. Technical Issues on PMAY Portal: Due to issues relating to gender correction on the PMAY portal, we were unable to upload beneficiary details in a timely manner. This resulted in a delay of approximately four months in receipt of the Government subsidy. 3. Heavy Rainfall (2025โ26): Excessive rainfall during the year 2025โ26 further impacted the progress of construction work. 4. Financial Constraints of EWS Beneficiaries: The beneficiaries under the project, belonging to the Economically Weaker Section (EWS), faced difficulties in availing housing loans from banks due to the absence of income tax returns. Consequently, there was a delay in receipt of payments towards the flats. We further submit that, as per the above-referred letter issued by the Ministry of Housing and Urban Affairs, Government of India, the PMAY-U Mission has been extended up to 30th September 2026 for completion of already sanctioned and ongoing projects. The present project squarely falls within the said category. We are pleased to inform that a scheduled bank has now agreed to extend housing loan facilities to the beneficiaries, and the process has recently commenced, which is expected to improve the pace of collections and construction. In view of the above facts and circumstances, and considering the extension granted by the Government of India under PMAY-U, we humbly request your good office to grant an extension of time up to 30th September 2026 for completion of the project. A copy of the above-referred Government letter dated 27.02.2026 is enclosed herewith for your kind perusal. We request your kind consideration and approval.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2022
- Floors
- 5
- Unit mix
- 1602 res ยท 5 comm
- Plot / CTS / survey no.
- GAT NO.1196/1 AND 1196/2
- Planning authority
- MAHADA
- Approved layout land
- 57,354 sq.m
- Land for this registration
- 57,354 sq.m
- Recreational open space
- 5,735.72 sq.m
- Permissible built-up area
- 1,87,568.08 sq.m
- Registered office
- BARSHI NAGAR PARISHAD
- North
- PART OF GAT NO 1196
- South
- GAT NO 1097
- East
- PIMPALGAON DHAS 30MTR ROAD
- West
- ROAD AND GAT NO 1062
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF MAHARASHTRA โ 90095IFSC MAHB0000051RAICHURKAR BUILDING GULAL ROAD BARSHI
Commencement Certificate documents
- COMMENCEMENT CERTIFICATE.PDF
- FORMAT D.pdf
- MAHADA PERMISSION.PDF
Buyer community
Connect with other buyers and owners of PMAY BARSHI NAGAR PARISHAD AHP โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PMAY BARSHI NAGAR PARISHAD AHP. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.