Under construction

SHAZNEEN GALAXYMahaRERA P52600051219

by NAZNEEN JAINODIN NADAF

S.No.118/1, P.No.23, Majrewadi, 413224

Dec 2026
Possession
25.5%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 25.5%.

Official RERA facts

Registration
P52600051219
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
25.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Mujahid Mustaque Shaikh

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone

Building & registration

RERA registered
Jun 2023
Floors
5
Plot / CTS / survey no.
S.No.118/1, P.No.23
Planning authority
Others
Approved layout land
278.7 sq.m
Land for this registration
278.7 sq.m
Permissible built-up area
713.39 sq.m
Promoter contact
NAZNEEN JAINODIN NADAF
Registered office
SHAZNEEN DEVELOPERS
Plot boundaries
North
plot
South
plot
East
Road
West
plot
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • IDBI BANK โ€” 61294
    IFSC IBKL0478MCB
    Shukarwar Peth

Commencement Certificate documents

  • 11zon_IMAGES-to-PDF (3).pdf

Buyer community

Connect with other buyers and owners of SHAZNEEN GALAXY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHAZNEEN GALAXY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.