PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIG

MahaRERA P52600056169Clean record

by Pune Housing and Area Development Board Pune

CTS No. 232, FP No. 86 (P) of TPS-03 of Modi, Soni Nagar, 413001

Official record
Dec 2032
Possession
37.6%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52600056169
Status
New
Stage
Certificate Signed
Possession
December 2032
Construction
37.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2024
Floors
8
Plot / CTS / survey no.
CTS No. 232, FP No. 86 (P) of TPS-03 of Modi
Planning authority
Others
Approved layout land
8,000 sq.m
Land for this registration
8,000 sq.m
Recreational open space
768.97 sq.m
Permissible built-up area
12,096.14 sq.m
Registered office
Grihanirman Bhavan
Plot boundaries
North
18 m Int road
South
Balanced land of CTS no 232
East
balanced land of CTS no 232
West
Pune Hyderabad Railway Track
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF MAHARASHTRA โ€” 90120
    IFSC MAHB0000076
    628/29 KHUDA MURAD SACHAPIR STREET , SARABATWALA CHOWK, CAMP PUNE 411001

Commencement Certificate documents

  • Commencement Certificate.pdf
  • Final Solapur BPMS Signed Certificate.pdf

Buyer community

Connect with other buyers and owners of Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIG โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Construction of Composite Housing Scheme of 126 T/s EWS and 112 T/s LIG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.