Under construction

HILL CREST PARKMahaRERA P52700003083

by LIMRA DEVELOPERS

GAT NO. 563 HISSA NO.3, Ajnuj, 412802

Dec 2026
Possession
โ€”
Built
0
Complaints
167
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52700003083
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
โ€”
Units sold
58 of 167

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplynot started
Street Lighting20%
Aggregate area of recreational Open Spacenot started
CIUB HOUSEnot started
Gates10%
Compound Wall30%
Tree Plantation30%

Building & registration

RERA registered
Aug 2017

Buyer community

Connect with other buyers and owners of HILL CREST PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HILL CREST PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.