Under construction

Aapla ghar Shirwal Phase IMahaRERA P52700007048

by Maple Aurus Realty

Gat No 242-1/A and 238-2 and 3, SHIRWAL, 415521

Dec 2022
Possession
53.4%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 53.4%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2022 per the RERA filing.

Official RERA facts

Registration
P52700007048
Status
Ongoing
Stage
Certificate Signed
Possession
December 2022
Construction
53.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Aapla ghar Shirwal Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aapla ghar Shirwal Phase I. Real notes from real buyers beat any brochure.

Start a discussion