Under construction

Triaa AashrayMahaRERA P52700013128

by EBPL HOMES LLP

Survey No. 410/1, GAT No. 605/1, Shindewadi, 412801

Sept 2025
Possession
86.8%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Sept 2018, now proposed Sept 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 86.8%.

Official RERA facts

Registration
P52700013128
Status
Ongoing
Stage
Certificate Signed
Possession
September 2025originally September 2018
Construction
86.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths65%
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drainsnot started
Landscaping & Tree Planting75%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station45%
Aggregate area of recreational Open Spacenot started
Open Parking40%

Building & registration

RERA registered
Sept 2017
Floors
4

Buyer community

Connect with other buyers and owners of Triaa Aashray โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Triaa Aashray. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.