Under construction

SWAPNDEEPMahaRERA P52700014600

by APURVA CONSTRUCTION

Survey Number 438/439/440, Plot Number 5, Lahsurne, 415501

Jun 2028
Possession
52%
Built
0
Complaints
74
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2021, now proposed Jun 2028 per the RERA filing.

Official RERA facts

Registration
P52700014600
Status
New
Stage
Certificate Signed
Possession
June 2028originally December 2021
Construction
52% complete
Units sold
7 of 74

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Electrical meter room, sub-station, receiving station95%
Open Parking80%

Building & registration

RERA registered
Dec 2017
Floors
6
Unit mix
46 res ยท 28 comm
Architect
ASHOK GAIKWAD

Buyer community

Connect with other buyers and owners of SWAPNDEEP โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.