SAMARTH RECEDENCYMahaRERA P52700016134
by URMODI BUILDER & DEVELOPERS
34/1/2, Jakatwadi, 415002
Aug 2025
Possession
88.2%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Sept 2022, now proposed Aug 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Aug 2025) has passed with construction at 88.2%.
Official RERA facts
- Registration
- P52700016134
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2025originally September 2022
- Construction
- 88.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Planting80%
Street Lighting75%
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Apr 2018
- Floors
- 5
Buyer community
Connect with other buyers and owners of SAMARTH RECEDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAMARTH RECEDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.