Under construction

BrahmashriMahaRERA P52700019397

by Ghaisas Developers LLP

2105/1, Waghmodewadi, 415540

Dec 2026
Possession
43.6%
Built
0
Complaints
18
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2020, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.6%.

Official RERA facts

Registration
P52700019397
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2020
Construction
43.6% complete
Units sold
15 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Electrical meter room, sub-station, receiving stationnot started
Open Parking60%

Building & registration

RERA registered
Jan 2019
Floors
3
Unit mix
18 res ยท 0 comm
Architect
SM Landage

Buyer community

Connect with other buyers and owners of Brahmashri โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Brahmashri. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.