SAMRUDDHI SRUSHTIMahaRERA P52700028731
141/142 PLOT NO 4, -, 415002
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P52700028731
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2021
- Floors
- 7
- Plot / CTS / survey no.
- 141/142 PLOT NO 4
- Planning authority
- Others
- Approved layout land
- 511.5 sq.m
- Land for this registration
- 511.5 sq.m
- Permissible built-up area
- 1,145.39 sq.m
- Registered office
- KONARK APPARTMENT
- North
- ADJOINING S NO 140 2 PLOT NO 30
- South
- 9 MTRS WIDE ROAD
- East
- 6 MTRS WIDE ROAD
- West
- ADJOINING S NO 143
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- UNION BANK OF INDIA โ 153578IFSC UBIN0906778SADARBAZAR SATARA
Commencement Certificate documents
- building permission.pdf
Buyer community
Connect with other buyers and owners of SAMRUDDHI SRUSHTI โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAMRUDDHI SRUSHTI. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.