EMPIRE TOWERSMahaRERA P52700030634
S.NO. 28 1 CTS NO. 6482 B PART 63, 66, 65, 64, 67 PLOT NOS. 1, 32, 33, 34 AND 35, NEAR NAMJOSHI PETROL PUMP, 415523
- Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 71.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2026 per the RERA filing.
Official RERA facts
- Registration
- P52700030634
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2026originally March 2025
- Construction
- 71.8% complete
- Units sold
- 33 of 110
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EXT52700027845Revised to March 2026
Empire Towers is a commercial project & current status of said project is as follows : Total Units 110 Units Occupancy Certificate Obtained 67 Units Sold Units 29 Units Possession Given 11 Units Consent obtained 7 Units Total Consent obtained 18 Units Total Percentage of consent 62.07 % Due to the slowdown in the market, entire units are not being sold. Therefore, construction of the remaining units (excluding the units that have received occupancy certificate) is going on as per market response. In view of this fact, it is requested that the said project is kindly be extended till 30/12/2026.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Sept 2021
- Floors
- 7
- Unit mix
- 0 res ยท 110 comm
- Architect
- SANKET JANGAM
- Plot / CTS / survey no.
- S.NO. 28 1 CTS NO. 6482 B PART 63, 66, 65, 64, 67 PLOT NOS. 1, 32, 33, 34 AND 35
- Planning authority
- Town Planning Satara
- Approved layout land
- 1,442 sq.m
- Land for this registration
- 1,442 sq.m
- Permissible built-up area
- 3,621.43 sq.m
- Registered office
- PUSHP PARK
- North
- ROAD
- South
- ROAD
- East
- ROAD
- West
- PLOT NO 36 AND PLOT NO 31
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 67404IFSC ICIC0006452SHIV RATAN TRAINING COLLEGE ROAD LAXMINAGAR PHALTAN
Commencement Certificate documents
- Permission.pdf
Buyer community
Connect with other buyers and owners of EMPIRE TOWERS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching EMPIRE TOWERS. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.