- Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P52700030810
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2024
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Chandrakant Ramji Patil
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Sept 2021
- Floors
- 6
- Plot / CTS / survey no.
- S No 15 Hissa No 4 Plot No 1
- Planning authority
- Others
- Approved layout land
- 719.5 sq.m
- Land for this registration
- 719.5 sq.m
- Permissible built-up area
- 1,611.67 sq.m
- Promoter contact
- Rajan Namdeo Pore
- Registered office
- Shivani Heights
- North
- S No 15 Hissa No 2 Plot No 1 2 3
- South
- S No 15 Hissa No 6
- East
- Road
- West
- Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 49190IFSC HDFC0000790Sadar Bazar Satara
Commencement Certificate documents
- commencement.pdf
Buyer community
Connect with other buyers and owners of Aditya Vihar โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Aditya Vihar. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.