Under construction

JAY TULJABHAWANI PARKMahaRERA P52700031751

by PANCHRATNA DEVELOPERS

GAT NO 71/2/1/1/1/2, VADUJ, 415506

Dec 2026
Possession
100%
Built
0
Complaints
64
Units
Caution
  • Possession delayed ~2 yrs. Originally promised May 2025, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52700031751
Status
New
Stage
Certificate Signed
Possession
December 2026originally May 2025
Construction
100% complete
Units sold
22 of 64

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

ANIL TUKARAM MALI, SUNIL TUKARAM MALI

Possession extension history

  • EA25092517942Revised to December 2026

    As we have started our project in 2022 at that time we have gone through effect of COVIDE 19 and so we are getting less response from market and customer. At that time we have decided to complete our project and complete but have not recived occupancy certificate from planning authority till date. So We want to extent our JAY TULJABHAWANI PARK. We already hand over sold flats to alloties, many of them have taken their flats possession and also give us censer for Rera Extension as their part of project is complete

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Nov 2021
Floors
8
Unit mix
51 res ยท 13 comm
Architect
PRAVIN BHADGAVE
Plot / CTS / survey no.
GAT NO 71/2/1/1/1/2
Planning authority
VADUJ NAGAR PANCHAYAT
Approved layout land
1,093.5 sq.m
Land for this registration
1,093.5 sq.m
Permissible built-up area
17,85,026 sq.m
Registered office
ARUN PLAZA , 1ST FLORE
Plot boundaries
North
9 Mtr Wide Road
South
gat no 76
East
Open Space
West
18 Mtr wide Road
Parking
17 four-wheeler20 two-wheeler2 visitor

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • Bank not specified
    IFSC IBLK0485SDC
    AT POST VADUJ TAL KHATAV DIST SATARA

Commencement Certificate documents

  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of JAY TULJABHAWANI PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching JAY TULJABHAWANI PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.