Under construction

Panchratna PremiumMahaRERA P52700046459

by Panchratna Premium

Survey No.150/2/A/1, Plot No.25, Malkapur, 415539

May 2025
Possession
0%
Built
0
Complaints
55
Units
High risk
  • Possession date passed. The proposed possession date (May 2025) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2025 per the RERA filing.

Official RERA facts

Registration
P52700046459
Status
New
Stage
Certificate Signed
Possession
May 2025originally March 2025
Construction
0% complete
Units sold
46 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA15072502067Revised to May 2025

    We, M/s. Panchratna Premium, hereby declare the following with respect to the project Panchratna Premium bearing registration number. P52700046459 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 13th May 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure a successful transition to occupancy. As a measure of assurance, we kindly request an extension until OC Date i.e - 13th May 2025, allowing us to complete all necessary procedures and meet our commitments to stakeholders while ensuring compliance with applicable regulations

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2022
Floors
10
Unit mix
43 res ยท 12 comm
Architect
Siddhiraj P Desai Architect and Interior Designer
Plot / CTS / survey no.
Survey No.150/2/A/1, Plot No.25
Planning authority
Malkapur Municipal Council
Approved layout land
1,373.05 sq.m
Land for this registration
1,373.05 sq.m
Permissible built-up area
4,139.19 sq.m
Registered office
Panchratna Park Co Op Hsg Soc
Plot boundaries
North
30 Mtr Wide Road
South
Plot No -26
East
Boundary of Emerson Company
West
12 Mtr Wide Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 48628
    IFSC HDFC0000165
    Hotel Sangam Pune Bangalore Highway Karad 415110

Commencement Certificate documents

  • building cc.pdf

Buyer community

Connect with other buyers and owners of Panchratna Premium โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Panchratna Premium. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.