Under construction

Siddharth towerMahaRERA P52700077951

by S K Developers

212A GODOLI, Nr. Sai baba Mandir, 415002

Dec 2030
Possession
40%
Built
0
Complaints
41
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52700077951
Status
New
Stage
Certificate Signed
Possession
December 2030
Construction
40% complete
Units sold
8 of 41

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2024
Floors
8
Unit mix
26 res ยท 15 comm
Plot / CTS / survey no.
212A GODOLI
Planning authority
Satara Municipal Council
Approved layout land
907.2 sq.m
Land for this registration
907.2 sq.m
Recreational open space
0 sq.m
Permissible built-up area
3,292.71 sq.m
Registered office
Siddharth tower
Plot boundaries
North
Municipal Road
South
Municipal road
East
Survey No 212 b
West
Municipal road
Parking
12 four-wheeler5 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • PUNJAB NATIONAL BANK โ€” 102684
    IFSC PUNB0195120
    SHOP NO 1 AND 2 OFFICE NO 1 RUKMINI KUNJ Guruwar peth, Satara 415002

Commencement Certificate documents

  • CC MAIL.pdf
  • commencement.pdf

Buyer community

Connect with other buyers and owners of Siddharth tower โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Siddharth tower. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.