Under construction

KADAMBARIMahaRERA P52800001167

by SANCHITA SACHIN KADAM

S.NO. 109 H.NO. 5/1. 29, 5/2. 37, 5/3. 38, 5/4. 39, Chiplun (M Cl), 415605

Dec 2028
Possession
88.6%
Built
0
Complaints
71
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Jan 2021, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52800001167
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally January 2021
Construction
88.6% complete
Units sold
42 of 71

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
5
Unit mix
64 res ยท 7 comm

Buyer community

Connect with other buyers and owners of KADAMBARI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KADAMBARI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.