Under construction

ANCHALITAS HACIENDASMahaRERA P52800002145

by VIKRAM PAYYAR

44/54, Adur, 415705

Dec 2026
Possession
32.6%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 32.6%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52800002145
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
32.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)5%
Storm Water Drains70%
Landscaping & Tree Planting30%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water5%
Solid Waste Management And Disposal5%
Water conservation /Rain water harvesting5%
Energy managemcnt25%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Space10%
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
1

Buyer community

Connect with other buyers and owners of ANCHALITAS HACIENDAS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANCHALITAS HACIENDAS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.