Siddhivinayak Nagar Lilly and RoseMahaRERA P52800003091

by Siddhivinayak Builders & Developers

344-2A-1,344-1-C,344-3-C,344-7,344-6, Ratnagiri (M Cl), 415612

Dec 2026
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52800003091
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Street Lighting20%
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station20%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of Siddhivinayak Nagar Lilly and Rose โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Siddhivinayak Nagar Lilly and Rose. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.