Under construction
VASHISHTHI DARSHANMahaRERA P52800008357
1651, Gowalkot, 415605
Dec 2026
Possession
65.9%
Built
0
Complaints
28
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800008357
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 65.9% complete
- Units sold
- 9 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains20%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station20%
Open Parking10%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
- Unit mix
- 28 res ยท 0 comm
Buyer community
Connect with other buyers and owners of VASHISHTHI DARSHAN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VASHISHTHI DARSHAN. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.